Who Gets the Train First?: Understanding Seattle’s Updated Sound Transit 3 Plan

Understanding Seattle's Sound Transit 3 Plan
Editors: James Hollander

Key Takeaways

  • Sound Transit, the Seattle area’s regional transit agency, faces a $34.5 billion funding gap over the next 20 years. In May 2026, its board responded by delaying and only partly funding several transit projects.
  • Scaled-back funding for the Ballard light rail extension has delayed the project while Sound Transit looks for more money. Trains could reach Ballard as early as 2042 or as late as 2060.
  • As infrastructure costs rise, delays in project completion will accumulate and decisions will need to be made on project priority.

Introduction

Sound Transit is the regional public transit authority for the Seattle metropolitan area. It oversees a system of commuter rail, light rail, and express buses. On May 28, 2026, the Sound Transit board adopted an updated plan for Sound Transit 3 (ST3), an ongoing expansion of the transit system. Voters approved the original ST3 plan in 2016, and it is funded through regional sales, vehicle, and property taxes. The new plan contains significant funding cuts to previously approved transit projects. 

The update was prompted by a projected $34.5 billion funding gap over the next 20 years. Sound Transit attributes the gap mainly to historic inflation and rising operating costs. Roughly $30 billion of the shortfall comes from increases in construction cost estimates compared to the original plan.

The updated ST3 plan addresses the budget gap in part by scaling back funding commitments and listing some projects as unaffordable under current funding conditions. The plan sorts projects into three groups: fully funded, funded only through design, and deferred until new money is found. Several projects have been modified, deferred, or labeled as unaffordable, but the most controversial change relates to the Ballard light rail extension, which is no longer fully funded to completion. This extension would bring light rail service from downtown Seattle to Ballard in northwest Seattle. 

For Ballard, construction of the first segment, from SODO to Seattle Center, is fully funded, but the remaining stretch, from Seattle Center to Market Street in Ballard, is funded only through final design.

Map of Proposed Project for the Light Rail Ballard Link Extension

 

Proposed Map for the Light Rail Ballard Link Extension (Source: Sound Transit)

Arguments in Favor of the Updated ST3

Supporters of the updated ST3 point out that the new plan addresses the financial reality. With a $34.5 billion funding gap, they argue that protecting the agency’s long-term financial stability is necessary to keep the system and its expansion plans going.

Additionally, while Ballard was not the only project to lose full funding in the updated ST3 plan, it was by far the most expensive remaining project of ST3. Sound Transit’s 2025 preliminary estimates place the full Ballard extension at $20.1 billion to $22.6 billion, up from about $11.9 billion in the agency’s earlier financial plan. Due to the nature of planning and environmental review timelines, supporters argue altering the project order to fund Ballard first would likely delay other ST3 projects. 

The updated ST3 still supports the Ballard extension, even without full funding for construction. Under the new plan, the design process for the Ballard extension remains fully funded. The board also required Sound Transit to publish a Ballard project timeline. On July 31, 2026, the agency announced that trains could reach Ballard by 2042 if it closes the project’s funding gap by 2033. Without new savings or funding, service could slip to 2060.

The updated ST3 plan also fully funds the construction of a second downtown tunnel from Seattle Center to SoDo, a neighborhood in southern Seattle. This tunnel would also act as a section of the Ballard line extension. Today, all Link light rail lines through downtown share one tunnel. Sound Transit says a second tunnel would let lines run separately, improving reliability. This tunnel would also serve as the first section of the Ballard line.

Arguments Against the Updated ST3

An argument against the new ST3 plan is that it prioritizes suburban areas at Seattle’s expense. While several infrastructure projects were impacted by the new ST3, Ballard was the only light rail extension removed from the list of funded projects; funding for suburban light rail extensions to Everett, Tacoma, and between South Kirkland and Issaquah was kept, although the Issaquah line was delayed to 2050. While relatively short, the Ballard extension connects dense population areas and has higher ridership projections than other projects. Sound Transit’s 2022 environmental review projected 132,000 to 173,000 daily riders on the Ballard extension by 2042, the highest of any ST3 project. This makes its delay potentially harmful to a comparatively large total ridership.

Additionally, Seattle has the only unfunded ST3 light rail extension, and proponents of the extension fear that this lapse in development will make it difficult for the city to approve future regional funding. To make things more precarious, some members of the Sound Transit board oppose additional funding through a hypothetical Sound Transit 4 plan. Without regional support, the funding of the Ballard extension will likely fall on Seattle alone.

Critics also point to ways to close the budget gap with fewer delays. Leaders including Issaquah Mayor Mark Mullet have proposed raising Sound Transit’s borrowing limit, or debt capacity. Under state law, Sound Transit cannot borrow more than 1.5 percent of the assessed value of property in its tax district without voter approval. Assessed value is the value the county assigns to property for tax purposes. If a ballot measure reaches approval from 60 percent of voters, the limit can rise to as much as 5 percent. Supporters argue that a 3.5 percent limit would let Sound Transit fund all ST3 projects without major new financial risk or further delays.

Conclusion and Future Outlook

The updated ST3 plan works to address significant budget shortfalls, but does so at the expense of a major high-ridership transit project for Seattle. As the design process for the Ballard extension continues, new details on potential savings and timelines will emerge. While Sound Transit navigates the difficulties of bringing light rail to Ballard, the debate over infrastructure priorities becomes increasingly relevant. As infrastructure costs in the United States continue to rise, transportation agencies and governments need to balance budgets with delivering necessary projects. Decision makers must consider how future transportation initiatives can both retain public trust and adequately balance local and regional priorities.

 

FREQUENTLY ASKED QUESTIONS:

The Sound Transit board of directors is made up of 18 members including 17 elected officials and the Washington State Secretary of Transportation. The 17 seats are assigned proportional to population, with 10 members from King County, four from Pierce County, and three from Snohomish County. Members include county executives, city council members, and mayors. 

Voters in the Sound Transit district approved ST3 in 2016. It is funded by an added 0.5 percent sales tax, an added 0.8 percent vehicle registration tax, and a property tax of up to 25 cents per $1,000 of assessed home value.

Sound Transit says the main cause is historic inflation: prices rose as much in six years as in the previous 20. Researchers also point to broader U.S. issues, such as lengthy public review processes, limited in-house agency staff, and heavy reliance on outside consultants.